Week 9 has seen ongoing work to foundations around the site. Some sections have had...
 
21st Mar 2011
The bricklayers have begun the task of building the foundations of the school. Hopefully...
 
11th Mar 2011
Week 6 has seen great progress to the school build. Remaining top soil has been...
 
4th Mar 2011
The retaining wall has now been completed paving way for construction of the school....
 
3rd Mar 2011
On Thursday 3rd March children from Key Stage one and Key Stage two celebrated World...
 
2nd Mar 2011
On Tuesday 1st March children from KS1 and KS2 took part in fun maths activities...
 
25th Feb 2011
On Thursday 24th February, children gathered to listen to samples of work...
 
25th Feb 2011
Concrete Shuttering continues.
 
22nd Feb 2011
On Tuesday 22nd February, children from schools across mid Armagh met for the annual...
 
18th Feb 2011
Concrete shuttering begins on the retaining wall.